You have the plans, the statement of environmental effects and a lodgement checklist from council. Somewhere on that list is an EDC report, short for estimated development cost, and it raises a fair question about who is allowed to prepare it and how much detail council expects.

The term is still fairly new in New South Wales, which adds to the confusion. It replaced capital investment value (CIV) in March 2024, and plenty of templates and advice still use the old terms. Getting the report right starts with knowing exactly what council means by the estimated development cost.

TL;DR

  • An EDC report sets out the estimated cost of a NSW development for the consent authority.
  • Who can prepare it depends on the project’s value, from the applicant up to a qualified quantity surveyor.
  • Projects over $3 million need a report in the standard form, dated within 30 days of lodgement.
  • The EDC excludes land costs and GST, which is shown separately.
  • Councils can question an estimate that looks out of line or sits close to a threshold.

What Is an EDC Report?

The estimated development cost is defined in section 6 of the Environmental Planning and Assessment Regulation 2021. Put simply, it is the estimated cost of carrying out the development. An EDC report is the development application cost estimate that shows how that figure was reached, so the consent authority can see what was included and why.

The term has applied since 4 March 2024. On that date, the NSW EDC framework replaced CIV and cost of development across the planning system, along with the cost thresholds that go with them. The current guidance is Planning Circular PS 25-004, issued in October 2025.

Once lodged, the figure does real work. It helps identify the assessment pathway and the consent authority (usually council, or a planning panel for larger projects), sets some application fees, and decides whether extra requirements such as design review apply. Section 7.12 contributions use a separate cost figure, though a quantity surveyor’s report can cover both.

Architectural plans, a hard hat and a compass on a desk, ready for an EDC report for a NSW development application

Who Can Prepare an EDC Report in NSW?

Who can prepare an EDC report in NSW depends on the estimated cost of the project. The higher the value, the more qualified the person preparing it needs to be, and above a certain point the report has to follow a set format. NSW Planning sets out four tiers.

  • Up to $100,000: you can prepare it yourself or use a suitably qualified person. A cost per square metre method is allowed for construction and fit-out.
  • $100,000 to $3 million: a suitably qualified person, with the method shown.
  • Over $3 million: a qualified quantity surveyor who is a member of a relevant professional body, such as the Australian Institute of Quantity Surveyors (AIQS) or the Royal Institution of Chartered Surveyors (RICS), using the standard form.
  • State significant development and infrastructure: an AIQS Certified Quantity Surveyor or a RICS Chartered Quantity Surveyor.

A suitably qualified person can be a builder licensed for the works, a registered architect, an accredited building designer or a quantity surveyor. Even in this range, a quantity surveyor’s EDC report is often the simplest option, because the method is already set out the way council expects. Anyone else needs proven experience costing work of a similar scale and type.

Above $3 million, the wording is worth reading closely. The planning circular says a quantity surveyor’s report is recommended, while NSW Planning’s EDC page says you must submit one, so treat it as required. Anything prepared at a lower tier tends to invite questions from council.

What the Standard Form EDC Report Includes

For projects over $3 million, NSW Planning publishes a Standard Form of Estimated Development Cost Report, released in March 2024. State significant projects have their own version. Both follow the AIQS practice standard, and the report is addressed to the consent authority, not the applicant.

The form has four parts. An executive summary, signed off by a qualified quantity surveyor, states the EDC and certifies that it is accurate and covers the full scope. The basis of preparation lists the plans relied on, any limitations and the surveyor’s qualifications.

The scope describes the proposal and every part of the work, including how the build will be staged. A calculation schedule then shows each cost, along with its assumptions and allowances for escalation and contingency.

A few practical rules sit alongside the form. The report can be dated no earlier than 30 days before you lodge, and GST appears three times: the EDC without GST, the GST itself, and the EDC with GST included. Different fees use different figures, which is why all three are needed.

What the Estimated Development Cost Covers

Section 6 of the Regulation sets out what goes into the estimated development cost and what stays out. Getting that split right matters, because counting the wrong items skews the figure just as much as missing them.

What’s Included

The EDC covers designing and constructing the building and its associated infrastructure, plus any other work in the development. Demolition and fixed or mobile plant and equipment are included too. Priced by element, these items also form an early project budget that stays useful after approval. Leaving out demolition or plant is a common reason an estimate comes in low.

What’s Left Out

Land costs are excluded, including marketing and selling. So are contributions or works required under conditions or a planning agreement, any part of the development with its own consent, and ongoing maintenance and running costs.

Breaking the cost down by element makes gaps and wrongly included items easy to spot. It also gives council a clear trail from the plans to the final number.

When Council Asks for an EDC Report

The estimated development cost report goes in with your application. That applies to a development application, a modification, a complying development certificate or a state significant application, so it is part of lodgement rather than something council requests later. How closely the figure is checked depends largely on the project’s value.

For projects under $3 million, PS 25-004 says it is best practice for councils to accept a residential EDC prepared in line with the circular. Non-residential projects can still be queried, and a figure from a general cost estimator often lacks the method council wants to see. Showing how each cost was reached avoids most of those questions.

Over $3 million, councils can have the estimate reviewed by an independent quantity surveyor. That review looks at the method as much as the total. A review is more likely when the figure looks out of line or sits within 10% of a threshold that changes the consent authority.

Getting the EDC Right the First Time

Most queries from council trace back to a handful of avoidable causes. They tend to surface after lodgement, when a delay holds up the whole assessment.

  • Plans that changed after the estimate was prepared
  • Demolition or plant and equipment left out
  • A builder’s price used as the EDC with no method shown
  • GST shown as one figure instead of three
  • A report more than 30 days old at lodgement, for projects over $3 million

The fix is an estimate built from current plans and priced by element, with the method written down. Bringing the estimate in before the plans are final means it can be updated quickly when the design changes. That is also what an independent reviewer looks for.

How ACP Prepares EDC Reports for NSW Councils

Every EDC report starts with your plans, specifications and application documents. ACP’s AIQS-certified quantity surveyors price the work by element and set it out so council can trace each figure back to the drawings, using the standard form wherever the project calls for it.

Reports go to councils across NSW, from metropolitan Sydney to the regions, backed by more than 25 years in business and a director with more than 40 years in quantity surveying. Pricing is fixed-fee, so you know the cost before any work begins.

Before You Lodge

Before you lodge, check which tier your project sits in, confirm what your council’s checklist asks for in the estimated development cost report, and make sure it reflects the final plans. Where a project sits close to a threshold, getting advice early usually costs less than answering a council query later. Those checks head off most of the queries that slow an application down.

This article is general information about NSW requirements rather than advice for a particular project. Your council’s lodgement checklist and the current NSW Planning guidance take priority, and both are updated from time to time.

Frequently Asked Questions

Can a builder’s quote be used as the EDC?

For projects under $3 million, a builder licensed for the work counts as a suitably qualified person, so their estimate can be used if it covers the full EDC scope and shows the method. Above $3 million, councils expect a quantity surveyor’s report in the standard form instead.

Is the EDC the same as the project budget?

The EDC follows the definition in the Regulation, so it leaves out land, GST and contributions that a full project budget would include. It is a planning figure for the consent authority, which is why it rarely matches the total you expect to spend.

Does a staged development need one EDC or several?

The EDC report should describe the whole development, including every stage, unless part of it already has its own consent. Council wants the full scope at lodgement, even when construction will happen in phases.

What happens if council thinks the EDC is wrong?

Council can ask for clarification or, for projects over $3 million, have an independent quantity surveyor review the estimate. The quickest way through is to send back the method and assumptions behind each cost, rather than a revised total on its own.